Project Update for the Week of February 5, 2024
Continuing with the Mezzanine framing in all wings, ensuring steady progress.
Sheetrock is set for delivery on Monday, with installation beginning on one side of the Mezzanine walls immediately.
Electricians are slated to start their work on the Mezzanine this week.
Plumbing efforts will proceed with core drilling in wings A & B, alongside necessary piping work in those areas.
The 1st Floor ladies' restroom will be available over the weekend (February 3-4), but please note it will be closed on Monday and Tuesday (February 5-6).
We are continuing to make progress on this important project!