Construction Project Look-Ahead Week of 4/14/25
Below is the project look- ahead for the week of 4/14/2025 PLEASE NOTE; We will be closing off apportion of the employees cafeteria one...
aohnotify
Apr 15
Construction Look-Ahead, Week of 3/31/25
Here's what’s happening on-site this week: ✅ 1st-floor HVAC ductwork and VRF lines are in progress ✅ 1st-floor D Wing electrical work...
aohnotify
Mar 28
Construction Look-Ahead, Week of 1/24/2025
Phase One project work look-ahead for the week of 1/24/2025. The excitement is building here at Andrus on Hudson. The first segment...
aohnotify